Tacoma Water Operations Building
Build a new Tacoma Water Operations Building
Tacoma Water is constructing a 60,000-square-foot warehouse and shop facility at 3506 South 35th St., south of the existing building. The new facility is for warehousing, hydrant, meter, and pipe shops, along with administrative and support spaces for our operations staff.
Why is Tacoma Water doing this now?
We learned we needed an updated facility after we received a 2016 seismic assessment of the existing 1939 building. The analysis found that the building would not be usable right after a major earthquake. Because this building is essential for our 24/7 water service operations, this project will help make sure we can continue supporting the community and restore services after a seismic event
The utility developed a 20-year master plan for the site between 2018 and 2023. Project goals include building a seismically resilient facility, making our operation’s site more efficient, improving how we use the facility and property space, and planning well for water service growth.
Who is involved?
The utility will deliver the project using the Progressive Design-Build method (this method encourages the utility to collaborate early with the contractor to make the design and construction more efficient) The Washington State Capital Projects Advisory Review Board approved the project. Tacoma Water selected Absher Construction and DLR Group architects as the Design-Build team, with Parametrix serving as the owner’s advisor. Tacoma Water staff offered feedback and input during this process.
Read our most recent updates
-

Crews are building the foundation for the new Water Operations Building. The building is designed to maintain operations after an emergency, so the thicker and wider foundation will support the highest level of seismic resiliency.
Crews have also started installing underground conduit and pipes. Next, they’ll pour the floor slabs. Depending on the weather, workers will pour the first slab in the fourth week of November.
Building materials, including more structural steel, will continue to arrive. We also expect more contractors on site in November to begin making other components, such as heating and ventilation ductwork. Construction is slightly ahead of schedule thanks to dry October weather.
Crews will begin required work along Tacoma Water’s frontage on the south side of South 35th Street. This work includes a new sidewalk, curb, and a bike lane.
Tacoma Water will continue working in the current building throughout construction.
Roadwork on South Burlington Way, along the southern edge of Tacoma Public Utilities’ property, and improvements to the intersection of South 35th Street and Union Avenue are part of a separate project.
-

Construction of the new building foundation is moving forward.
Crews are preparing the footings, and poured the first concrete on Oct. 2. They plan to pour more concrete each week until they finish the foundation.
Crews are also receiving materials, including structural steel, and installing underground utilities. Their focus is installing the stormwater systems for the new facility.
Tacoma Water will continue working in the current building throughout construction.
Roadwork on South Burlington Way, along the southern edge of Tacoma Public Utilities’ property, and improvements to the intersection of South 35th Street and Union Avenue are part of a separate project. This work is not part of the Tacoma Water construction project.
-
Over the past few weeks, crews removed the loading dock and canopy during to make room for the new building just south of the current Operations Building. They also separated and recycled demolition materials. In August, crews installed the sanitary sewer that will serve the new building.In September, crews will continue relocating utilities and begin pouring the building’s footings.
Employees will continue using the current Operations Building while crews build the new facility.
Work also continues on South Burlington Way, a new access road along the south edge of our property. A separate project includes the roadway; the Operations Building construction project doesn’t include that work.