Tacoma Power’s Electrical Construction Standards are requirements for residential and commercial electrical construction and maintenance.
CUSTOMER REQUIREMENTS
Standard # Standard Title
A-UG-1150 Precast Concrete Vault Applications & Specifications (Revised November 2, 2009)
A-UG-1200 Padmounted Transformer, Location Requirements (Revised November 20, 2007)
C-SV-1100 Meter Pole Requirement & Installation (Revised July 12, 2007)
C-SV-1200 Underground Secondary Service Box - Residential (Revised December 3, 2007)
C-SV-3000 Customer Transformer Service Vault (Revised August 5, 2002)
C-SV-3200 Commercial Secondary Service (Revised May 6, 2010)
C-SV-3250 Commercial Un-metered Service (Revised May 3, 2010)
C-SV-4000 Downtown Secondary Network Service (Revised July 19, 2002)
C-SV-5100 Voltage Flicker Limits (Revised October 28, 2002)
C-UG-1100 Conduit Installation (Revised March 10, 2005)
C-UG-1150 Custom Vault Installations (Revised September 28, 2005)
C-UG-1200 Pole Conduit Riser (Revised May 6, 2010)
C-UG-1300 Joint Utility Trench (Revised August 4, 2008)
C-UG-1400 Primary Pad-Mount Equipment Guard Post Installation (Revised January 2, 2002)
C-UG-1500 Primary Junction Box Installations (Revised November 2, 2004)
C-UG-1700 Pad-Mount Transformer Vault Installation (Revised March 12, 2007)
C-UG-2000 Precast Concrete Vault, Approved Vendors (Revised May 16, 2007)
C-UG-8000 Vegetation Management for Underground Systems (Revised May 30, 2002)
C-UG-9000 Installation of Street Lights with Underground Supply (Revised November 19, 2003)
C-MR-0020 Unsupervised Meters (December 17, 2009)